Successes:
-
Completed study materials for user feedback round #1
-
Have clearly defined plans and methods to conduct user feedback
-
Received and implemented valuable comments from Zebra team to supplement our initial plan
-
-
Completed initial Figma prototype/design concept
-
Made changes based on Zebra’s feedback about our sketch prototype
-
Made changes based on in-class feedback from another group
-
-
Felt confident in the direction of our design
Failures:
-
Unable to start user feedback and testing
-
Prototyping took longer than anticipated, and we pushed back our timeline for user testing
-
-
The Figma prototype was not fully ready for user testing this week
Difficulties:
-
Half of our team could not attend class on Tuesday, had to coordinate additional tasks outside of class time and relay feedback on prototype
-
Managing the quick turnaround for submitting/completing prototypes
Goals for Next Week:
-
Complete user feedback results round #1
-
Get in contact with people we originally interviewed for research and reach out to other potential audiences
-
Analyze & apply feedback to second prototype iteration
-
-
Continue iterating/editing prototype
-
Implement any changes suggested in weekly Zebra meeting
-
Implement Zebra design guide into our prototype
-