Weekly Status Update #9

Week of April 10

Team Members: Sonia Mody, Talia Smith, Andres Antonio, Evan Zlotnick

post-user-testing-questions.png
Successes: 
  • Completed first round of user feedback

    • Each group member found a potential user to interview and receive tangible feedback on all pages of the prototype (did 4 tests)

    • We got a lot of valuable feedback that will inform our next prototype

  • Started user feedback results round #1 document

    • Started compiling main points of feedback to focus on for second prototype iteration

  • Received feedback from Zebra about first prototype iteration

    • Learned which pages they want us to focus on for the second iteration

    • They really liked the recognition page and the “game of the day” idea

Failures: 
  • We were not able to recruit testing participants from the interviews we conducted during our discovery phase

    • All of the users we tested where in the same demographic - lack of diversity

Difficulties:
  • Finding users to test the prototype on

    • Many users who gave their email did not respond to this second round of testing

  • Creating a schedule/staying on pace for future deadlines

    • Meeting deadlines for class as well as being prepared for upcoming Zebra meetings

  • Finding time for us to all meet and work on our upcoming assignment

Goals for Next Week: 
  • Revise our prototype and create a second iteration

    • Go into figma and adjust existing pages to address user, Zebra, and class feedback

    • Create new pages to address features that are lacking

    • Implement Zebra’s design guide

  • Start & complete study materials for user feedback round #2

    • Prepare script and procedure for a second round of testing